  1. Early work underway at Gravity Experience Park
  2. UA Community Center continues to rise at Kingsdale
  3. Anybody know what's being built behind the BP station along East Broad near Parsons? (The big plot of land that stretches from 18th to Monroe)
  4. I double checked with a couple workers. While they didn't know exactly what they were doing to the walkway, they both said that's what they're working on!
  5. Looks like work is starting this week on the Elevated Park Downtown
  6. From 4th & 5th Wood framing has started on the housing that will stretch along 4th And a couple from the east side of the site
  7. Progress check on the office building going up at Astor Park
  8. Wood framing has started to rise at the Peer on 7th And you can see it just beginning to rise in the distance
  9. Work is wrapping up on the new football stadium at Gahanna High School- The new high school itself, which will be built next to the stadium, appears close to starting vertical construction as well
  10. Crews are tearing up the old parking lot at Starling Middle School today ahead of the upcoming construction
  11. Couple quick ones of the new apartment complex going up along Rathmell, adjacent to Google, called the Orchards Nice to see so many projects on the far south side!
  12. New freeway wall rising near Short Street as part of the Downtown Ramp Up project
  13. After a slow start, things are beginning to pick up at the Parsons Solar Field Project, located across Parsons Ave from the Google Data Center site on the far south side. Kind of hard to see because I couldn't get real close but it's much busier out here today than I've seen so far The first data center going up across the street at Google can be seen in the distance: https://news.wosu.org/politics-government/2023-05-04/columbus-breaks-ground-on-two-new-solar-arrays-that-could-power-up-to-7-500-homes
  14. Got a few quick ones of the Columbus Castings site while I was stopped in traffic Edit: Forgot I had a couple more (from Sunday)
  15. Mount Carmel West redevelopment ramping up
  16. Crews are tearing down the smaller structures next to the Drake today- I snatched a couple quick ones on my way through but between the concert traffic and construction in the area it was next to impossible to stop
  17. Tree clearing underway near the Souder Ave bridge
  18. Kind of hard to see but it looks like the Pharmavite facility is vertical